Monday, November 16, 2015


Work completed Last Week:

·         Completed replacement of sanitary sewer main at Magnolia St. and Lilac Ave..

·         Completed water main relocation at Magnolia St. and Lilac Ave.

·         Began storm sewer work on Magnolia St.

·         Began excavation of Stormtrap underground detention system.

 

 

 

Work Anticipated This Week:

·         Complete excavation of Stormtrap underground detention system.

·         Frame and pour Stormtrap concrete foundation late this week or early next week.

·         Excavate and pour concrete sidewalk, driveway and curb & gutter.

Friday, November 6, 2015


Work completed Last Week:

·         Began replacing sanitary sewer main under the proposed underground detention system at Magnolia St. and Lilac Ave..

·         Began installation of water main by means of directional drilling at Magnolia St. and Lilac Ave.

 

Work Anticipated This Week:

·         Complete replacement of sanitary sewer main at Magnolia St. and Lilac Ave..

·         Complete water main relocation at Magnolia St. and Lilac Ave.

·         Begin excavation and prep for sidewalk on Magnolia St.

·         Begin storm sewer work on Magnolia St.

Tuesday, November 3, 2015

Work Completed Last Week:

Mobilize traffic control, materials, equipment and personnel along with miscellaneous preparation work prior to starting construction.

 

Work Anticipated This Week:

Curb & gutter and sidewalk removal on Magnolia St.

Sanitary sewer removal and replacement located in the empty lot between 1556 and 1610 Magnolia St.

Excavation of pits and directional drilling water main to be relocated in the empty lot between 1556 and 1610 Magnolia St.