Thursday, October 22, 2015


Welcome to the 2015 Flood Relief Construction Blog!  Each week updates will be given regarding the construction progress from the following week, anticipated work to occur the upcoming week, and other information. Additional information will also be provided on a periodic basis via mailed or hand-delivered letters. These construction updates will typically provide more time-sensitive information.  Please be on the lookout for these updates in the mail or in your front door.
The project consists of construction of an underground detention system, storm sewer construction, storm structure installation and replacement, water main relocation, utility trench paving, curb and gutter repairs, sidewalk construction, and restoration.

The general contractor for the project is A. Lamp Concrete Contrators, Inc. The Village of Glenview’s Project Manager is Chris Gray and the Village’s on-site construction representative is Joe Molidor.

Work Completed Last Week:

An onsite meeting with Village staff and contractor was conducted last week to determine work schedule, construction operations, and set expectations for project.

Work Anticipated This Week:

·         Mobilize equipment and personnel along with miscellaneous preparation work prior to starting construction.

·         Begin tree removal and fence removal.