Tuesday, November 3, 2015

Work Completed Last Week:

Mobilize traffic control, materials, equipment and personnel along with miscellaneous preparation work prior to starting construction.

 

Work Anticipated This Week:

Curb & gutter and sidewalk removal on Magnolia St.

Sanitary sewer removal and replacement located in the empty lot between 1556 and 1610 Magnolia St.

Excavation of pits and directional drilling water main to be relocated in the empty lot between 1556 and 1610 Magnolia St.

 