Monday, November 16, 2015


Work completed Last Week:

·         Completed replacement of sanitary sewer main at Magnolia St. and Lilac Ave..

·         Completed water main relocation at Magnolia St. and Lilac Ave.

·         Began storm sewer work on Magnolia St.

·         Began excavation of Stormtrap underground detention system.

 

 

 

Work Anticipated This Week:

·         Complete excavation of Stormtrap underground detention system.

·         Frame and pour Stormtrap concrete foundation late this week or early next week.

·         Excavate and pour concrete sidewalk, driveway and curb & gutter.